Pomona College Museum of Art Construction

Print
Press Enter to show all options, press Tab go to next option

 Renwick Lot 7

The City Council approved the Pomona College Master Plan Environmental Impact Report (EIR) and related zone changes in February 2016. In May 2017, the City Council approved the architectural design of the Pomona College Museum of Art and the relocation of Renwick House. The Renwick House has been relocated and site work is underway for the Museum of Art.

Master Plan Oct 2015

Pomona College 2015 Master Plan - Recirculated Draft EIR

Pomona College Master Plan Historical Resources Technical Report

Pomona College 2015 Campus Master Plan - Addendum to the Final EIR

For more information, please contact the Community Development Department at (909) 399-5484.

To leave a comment after business hours, please call (909) 399-5398 or fill out the online form below.

Mitigation Measure Reporting & Public Input

Please correct the field(s) marked in red below:

Please share with the City your question or comment on the Pomona College Museum of Art construction. Your inquiry will be responded to within seven days. Thank you.

1
Name
2

Contact Information

 *
3
Comment:
 *
Comment:
4

Attachment

  1. To receive a copy of your submission, please fill out your email address below and submit.